Targets: Testnet v0.5
Resources Required:
- 1 Delivery engineer
- DST
Store Sync — Hardened reviewed and fixed the Store Sync protocol in Testnet v0.4. DST validates it in Testnet v0.5.
Exit criteria
- Expected reliability and performance of Store Sync are agreed with DST.
- DST signs off Store Sync against those expectations.
Risks
| Risk | (Accept, Own, Mitigation) |
|---|---|
| DST findings late in the cycle | Run the first DST pass in the first half of the cycle, so there is time to fix what it finds. |
Deliverables
DST sign-off for Store Sync
Owner: Delivery Team + DST
Done when: A DST report covering the agreed expectations is available and signed off.
Address Store Sync issues found by DST
Owner: Delivery Team
Store Sync issues found by DST are triaged and fixed.
Done when: No P0 or P1 issues found by DST remain open.