Week 40 2026 (Mon Sep 28 - Fri Oct 2, 2026)

Highlights

Large Data Transport Layer for Mix

  • achieved:
    • MixTransport SPEC first draft approaching review-ready status
    • helping in testing storage with Mix in the Logos Basecamp
  • next:
    • wrapping out the spec
    • preparation for the off-site

Hidden Services Over Mix

  • achieved:
    • prepared for the research call covering path compromise and selection strategies: slides
    • demo for the simulation and path selection strategies demo
  • next:
    • continue work on the second iteration of hidden service spec with the path selection spec.
    • prepare offsite talk/discussion points on hidden services and path selection specs.

Package Manager

  • achieved:
    • General effort on deploying to test and fixing issues